A new system aims to screen out speculative projects and group large electricity users seeking grid connections for faster ...
The first projects to navigate the process will be called “Batch Zero." The Electric Reliability Council of Texas says its ...
Texas’ Public Utility Commission has approved a new connection process proposed by the Electric Reliability Council of Texas ...
Officials say the batch study will allow ERCOT to better manage large electricity-hungry users.
The Public Utility Commission of Texas (PUCT) approved the Electric Reliability Council of Texas’s (ERCOT’s) process for ...
The Electric Reliability Council of Texas, the state's grid operator, is expecting load growth of up to 150 GW by 2030, he said — while the system's 2024 peak was about 86 GW. The rapid growth ...
As data centers seek to tap Texas’ energy, grid regulators are close to approving a new way of vetting requests ...